Latest update of Anambra cargo and pessengers airport .
1, Tollest Control Tower in Nigeria almost completed
2, The 3.7 km runway second longest in Nigeria and longest in eastern region to be able to accommodate large aircraft is almost completed
3, the terminal building is taking shape, it's three floors with lift to be installed
4, Apron and taxi way has been completed
NB
The Airport is 100% being funded by Anambra state government
Same way IMO airport is 100% funded by Imolites.
Construction companies handling the Airport projects
CRCC, Crainburg, Nigercat, IDC and Kanubeen
Steadily..we’re getting there
I saw the icc in awka being constructed..wasn’t impressed By the roof selection
1, Tollest Control Tower in Nigeria almost completed
2, The 3.7 km runway second longest in Nigeria and longest in eastern region to be able to accommodate large aircraft is almost completed
3, the terminal building is taking shape, it's three floors with lift to be installed
4, Apron and taxi way has been completed
NB
The Airport is 100% being funded by Anambra state government
Quote:The Airport is 100% being funded by Anambra state government
Same way IMO airport is 100% funded by Imolites.
Construction companies handling the Airport projects
CRCC, Crainburg, Nigercat, IDC and Kanubeen
Steadily..we’re getting there
I saw the icc in awka being constructed..wasn’t impressed By the roof selection
Quote:
1, Tollest Control Tower in Nigeria almost completed
2, The 3.7 km runway second longest in Nigeria and longest in eastern region to be able to accommodate large aircraft is almost completed
3, the terminal building is taking shape, it's three floors with lift to be installed
4, Apron and taxi way has been completed
NB
The Airport is 100% being funded by Anambra state government