The following warnings occurred:
Warning [2] Undefined array key "avatartype" - Line: 783 - File: global.php PHP 8.0.30 (Linux)
File Line Function
/global.php 783 errorHandler->error
/printthread.php 16 require_once
Warning [2] Undefined array key "avatartype" - Line: 783 - File: global.php PHP 8.0.30 (Linux)
File Line Function
/global.php 783 errorHandler->error
/printthread.php 16 require_once
Warning [2] Undefined variable $awaitingusers - Line: 16 - File: global.php(844) : eval()'d code PHP 8.0.30 (Linux)
File Line Function
/global.php(844) : eval()'d code 16 errorHandler->error
/global.php 844 eval
/printthread.php 16 require_once
Warning [2] Undefined array key "showimages" - Line: 160 - File: printthread.php PHP 8.0.30 (Linux)
File Line Function
/printthread.php 160 errorHandler->error
Warning [2] Undefined array key "showvideos" - Line: 165 - File: printthread.php PHP 8.0.30 (Linux)
File Line Function
/printthread.php 165 errorHandler->error



Forums
FG mobilizes contractors back to site for Akanu Ibiam International Airport Enugu com - Printable Version

+- Forums (http://contripeople.com)
+-- Forum: General Discussion (http://contripeople.com/forumdisplay.php?fid=5)
+--- Forum: Market Place (http://contripeople.com/forumdisplay.php?fid=77)
+--- Thread: FG mobilizes contractors back to site for Akanu Ibiam International Airport Enugu com (/showthread.php?tid=34163)



FG mobilizes contractors back to site for Akanu Ibiam International Airport Enugu com - Edoman - 06-02-2020

Flight resumption: Airlines can not break even on 40% load factor, Olowo




FG mobilizes contractors back to site for Akanu Ibiam International Airport Enugu completion


[Image: enugu-oqdu7yysxjnxjv61iiodur974nkxlodakv...C219&ssl=1]
Runway resurfacing at Akanu Ibiam International Airport
FG mobilizes contractors back to site for Akanu Ibiam International Airport Enugu completion


Share


WORK at the Akanu Ibiam International Airport Enugu will soon be restarted as the Federal Government of Nigeria has announced remobilization of contractors back to site, to complete the rehabilitation of the runway and terminal buildings

The Minister of Aviation, Sen. Hadi Sirika disclosed this on his twitter handle @hadisirika today saying, “We announce our full remobilization to Enugu despite COVID-19 lockdown.


“Even with challenges like heavy rains, opening up of quarries and bitumen sources we should complete this procurement in few weeks,” the minister commented.  


Sirika assured the completion date of the works will be made known at his next inspection visit to the airport. “A definite date of completion will be announced at my next site visit”, he said.


Recall, Minister of Aviation on 31st March 2020 regretfully announced Federal Government’s inability to meet up it’s then April deadline suspending reconstruction work due to the global effects of the COVID-19 pandemic.


He had then explained that the runway rehabilitation project  had gone beyond 90 per cent, and would have been delivered in six to seven days but that the workers had to leave to be with their families in these trying times.


He said, “Considering that the construction workers have downed tools owing to the COVID-19 pandemic, the Federal Government, hereby, officially announces suspension of procurement. 


The work would have been completed in six to seven days, but the workers left to be with their families in view of the social distancing,” the minister stated.